Save PPM project back into PPM from MS project

  • 1.  Save PPM project back into PPM from MS project

    Posted Jul 08, 2019 10:27 AM
    Hi 

    I have installed CA PPM integration add in into MS Project 
    MS project versionInstalled 32 bit of the Plug in the new interface 
    using CA PPM v 15.5.1

    Question

    I can save a schedule from MSP into PPM
    But after opening a Project in MSP and adding new task from an excel spread sheet.
    I get this error  Project Save failed 
    My you please advise me what might be the cause of this error
    If someone have ever faced such or if there are any logs we can check to find the full details of this error

    The resources are okay, Task Names do not exceed the PPM Limit

    Thank you



  • 2.  RE: Save PPM project back into PPM from MS project

    Broadcom Employee
    Posted Jul 09, 2019 01:42 AM
    Hello Sibusiso,

    This version of MSP is not supported when using Clarity PPM 15.5.1 (MSI-based is the supported version). I cannot guarantee that the issue is not coming from here.

    Are you copy/pasting the tasks from another existing project file? Please check this: https://ca-broadcom.wolkenservicedesk.com/external/article?articleId=10395

    Best regards


  • 3.  RE: Save PPM project back into PPM from MS project

    Posted Jul 09, 2019 02:13 AM
    Hi 
    I have tried other options, like trying another MSP schedule,  it does save without issues,  so I was thinking it might be with some fields in my MSP project schedule which are causing this ,
    With this error it is just that it doesn't give the details of the actual problem. 

    I am hoping from your experience  what usually causes the integration to bring such an error ,
    Cause when its resources, task name exceed ppm limit it does specify.

    Thank you


  • 4.  RE: Save PPM project back into PPM from MS project

    Broadcom Employee
    Posted Jul 09, 2019 02:26 AM
    Did you check the KB article I sent? This may come from a copy/paste issue. As you mention that the issue appears after adding a task from an Excel spreadsheet, can you try the same steps and instead of copy/pasting, type the information instead?


  • 5.  RE: Save PPM project back into PPM from MS project
    Best Answer

    Posted Jul 09, 2019 10:03 AM
    I would check the app-ca.log on the Clarity server (if you are in a SaaS env, change the action in the url to #action:security.logs if you are logged in as an administrator).

    Sometimes issues with misconfigured MSP Field Mappings, NSQL lookup queries on a (e.g. task) attribute that isn't working correctly, etc., won't always yield a clear error in the MSP interface; sometimes you'll even get no error at all initially, until you try to do some later action like saving.  Things like that, but a list of things that aren't exhaustive, so you have to check where else the error details can be found to try and get a better idea of where to begin.


  • 6.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 03:22 AM
    Hi 

    I have checked the app-ca.log
    I find this error
    ERROR 2019-07-08 09:11:24,297 [http-nio-80-exec-189] clarity.ui (clarity:admin:5618085__B90539BB-CCE6-442B-9023-A148D4BC0890:projmgr.projectProperties) UI_MSG[:Mon Jul 08 2019 09:12:54 GMT 0200 (South Africa Standard Time):(TypeError): Cannot read property 'n' of null--Client Side Exception
    com.google.gwt.core.client.JavaScriptException: (TypeError): Cannot read property 'n' of null

    and
    ERROR 2019-07-08 09:11:24,312 [http-nio-80-exec-189] clarity.ui (clarity:admin:5618085__B90539BB-CCE6-442B-9023-A148D4BC0890:projmgr.projectProperties) UI_MSG[:Mon Jul 08 2019 09:12:54 GMT 0200 (South Africa Standard Time):One or more exceptions caught, see full set in UmbrellaException#getCauses--Client Side Exception
    com.google.gwt.event.shared.UmbrellaException: One or more exceptions caught, see full set in UmbrellaException#getCauses



  • 7.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:14 AM
    Hi,
    start and finish dates are correct? In MSP they can be empty, in clarity not.
    Are you using Text1 or Text3 fields?
    Regards

    ------------------------------
    Operation Manager
    Beta80
    ------------------------------



  • 8.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:14 AM
    Hi
    start and finish dates are correct? In MSP can be empty, in clarity not.
    Are you using Text1 or Text3 fields ?
    Regards

    ------------------------------
    Operation Manager
    Beta80
    ------------------------------



  • 9.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:15 AM
    Hi
    start and finish dates are correct? In MSP can be empty, in clarity not.
    Are you using Text1 or Text3 fields ?
    Regards

    ------------------------------
    Operation Manager
    Beta80
    ------------------------------



  • 10.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:14 AM
    Hi,
    start and finish dates are correct? In MSP can be empty, in Clarity not.
    Are you using Text1 or Text3 fields?
    Regards

    ------------------------------
    Operation Manager
    Beta80
    ------------------------------



  • 11.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:15 AM
    Start and finish date are correct ? In MSP can be empty, in Clarity not.
    Are you using Text1 or Text3 ?

    regards

    ------------------------------
    Operation Manager
    Beta80
    ------------------------------



  • 12.  RE: Save PPM project back into PPM from MS project

    Posted Jul 10, 2019 09:58 AM
    Hi 

    I have been checking from the logs as mentioned or suggested 
    looking at the error suggesting that there is a null value ''N''
    I double check my schedule in MS Project I found that when I import it from excel it adds extra fields at the bottom of my schedule (just question marks without any words)
    So I had to remove all the extra lines It does go through, only if my Mapping from excel I  included tasks not resources and assignments

    when I include resources and assignments i brings the same error
    I am still checking what might be the cause


    Thank you for your support