  • 1.  Updating Cost Plans in Bulk?

    Posted Jan 10, 2019 06:24 PM

    Hey, 

     

    We have cost plans created for all of our projects, but the cost plans do not update when a resource's allocation or capitalization % change. You can force an update by going into each individual cost plan and hitting Actions > Populate from Investment Team, but that's a lot to track and so much extra work.

     

    Is there a job I can run or anything I can do to force ALL cost plans across all projects to pick up updates?

     

    Thanks!



  • 2.  Re: Updating Cost Plans in Bulk?

    Posted Jan 10, 2019 06:31 PM

    Also for clarification -- I want to update planned costs.



  • 3.  Re: Updating Cost Plans in Bulk?

    Posted Jan 10, 2019 06:43 PM

    You may have to rely on custom script/process, I reckon. How many projects you are planning to update in bulk approx.?



  • 4.  Re: Updating Cost Plans in Bulk?

    Posted Jan 11, 2019 04:46 PM

    Hey pdesur, thanks for the response. Right now, it's several hundred projects, and that number is only going to get bigger