Clarity

 View Only
  • 1.  Input historic baseline to project with actual hours assigned

    Posted Jan 22, 2018 06:19 PM

    I want to show project actual vs. baseline performance, for a project that was not managed well in CA PPM.  Project  consists of a few tasks with actual hours booked.  Allocations were developed, but not input to CA PPM (alas, Excel....).  Actuals have exceeded the allocated hours forecasted in Excel - otherwise, this wouldn't be an issue.

     

    I've successfully input these Excel allocations into the project in CA PPM (Created three new tasks, assigned roles, removed the tilde from "effort" task, set ETC's to zero on old tasks, assigned the allocation hours to the roles assigned to the tasks, set allocations from estimates - viola!  Good, so far.)

     

    Now, I need to baseline these new tasks which contain my original forecast from Excel.  Once baselined, I can set ETC to zero on these new tasks, to show that my actuals have overrun the original forecast - this is the reality of this project.

     

    Unfortunately, it appears CA did a really good job of preventing anyone from cheating their baselines:

     

    - creating baseline in CA PPM - no way to do this without actual hours baselined

    - editing baseline in MS Project (delete baseline work, delete tasks, create baseline only for selected tasks,.....) and then saving to CA PPM - no way to do this - CA PPM always appears to figure out that you've cheated and won't save your MS Project cheats

    - even tried to use a 'journal entry' task with negative hours to offset the actual hours when baselining - but MSP won't accept negative hours on a task

     

    Of course, the lesson hear is to do it right, right from the beginning.

     

    But my customer wants to see what could have been seen had the project been run properly in CA PPM.  We know this project had issues, we have the data in various spots, but not all in CA PPM - if it were there, what would it have shown the project manager and his management and when?

     

    Basically, I need some kind of administrative workaround that let's me ignore actual hours already booked when inputting the baseline that should have been there from the start of the project.

     

    One workaround, would be to create a new project with just the forecast in it, baseline it, then set ETC to zero and attach the original as a child project.  But most of the out of the box portlets and reports don't support this parent/child roll-up/comparison.

     

    Another workaround is to put the allocated hours and costs into a Cost Plan, submit it as Budget - I know this quite well.  This is actually part of our plan and I know this works - but, it doesn't help with the WBS based metrics

     

    Any ideas? 



  • 2.  Re: Input historic baseline to project with actual hours assigned

    Posted Jan 22, 2018 09:15 PM

    As far as I know, there's no way to "cheat" the baseline.  My guess is that prevents a dodgy PM from bribing their PMO Director with whiskey to make their project look green and happy (not that I'd take bribes from dodgy PMs, of course! And certainly not good quality single malt scotch!)

     

    How "historic" are your timesheet actuals?  Is it feasible to send the timesheet back, zero out the hours, baseline the project, re-post the timesheet? I think that's the only way to get the baseline sans actuals.



  • 3.  Re: Input historic baseline to project with actual hours assigned

    Posted Feb 08, 2018 10:12 AM

    So, a Colt 45 Malt won't do.   Hmmm...this could get expensive, I see.

     

    I will recommend that we consider such projects 'out of scope.'  The amount of timesheets to deal with are too great (our projects typically last 2-4 years, and this example is pushing past 4).  Also, there is the cascading impact on financial transactions.

     

    - May we get what we want

    - May we get what we need

    - May we never get what we deserve

     

    Cheers!



  • 4.  Re: Input historic baseline to project with actual hours assigned

    Posted Feb 08, 2018 02:25 PM

    Colt 45 from most of the PMs would do the trick. I'd hold out for the Glenmorangie from some of them, though!