Senthil Kumar Lakshmanan escreveu:
Here is the solutions.
Solution 1:
You need to add additional BG to handle more no of process instance.
Solution 2:
You need to clean up the old running process instance.
Ex: if some of the processes are waiting for approval for long time period (More than 6 months), You can extract the information and ask approver to perform their actions.
Temp Solution:
Go to Process Engines and click on Process Name --> Click on Run Event-Waiting Steps and verify whether approved/rejected AI moved to next Step.
Thanks
Senthil
Hi Senthil!!
About solution 1, it is very interesting.
We don't have processes waiting for approval, for more than 1 month, for example.
I tryed run "Run Event-Waiting Steps", but this did not work.
I believe this is a problem.
Thank you!