Hi Kristin,
No baseline - so #1 is out. And, we've never used MSP Enterprise, nor has this project ever been exported to MSP before - expect #2 is out.
I'm not getting the 'SchedLink MFC Application has stopped working' error, but I do see "The last time you opened 'PRJ00088.xml', it caused a serious error. Do you still want to open it? " message.
Also, the XML file contains dates in 2079, even availability dates of 2149. May we live that long!
- <Rate>
<RatesFrom>1900-01-01T00:00:00</RatesFrom>
<RatesTo>2079-06-03T00:00:00</RatesTo>
- <AvailabilityPeriods>
<AvailabilityPeriod>
<AvailableFrom>1984-01-01T00:00:00</AvailableFrom>
<AvailableTo>2149-12-31T23:59:00</AvailableTo>
Is this sufficient evidence for your #3?
If yes, will try the workarounds suggested in the associated link.
One question regarding: "These errors occurs when another resource/role has been staffed on the project Team after the Rate Matrix Extraction job has already run and there are already records in the nbi_proj_res_rates_and_costs for other resources/roles on that project.
- The RME job is regularly scheduled
- We staff projects, and then later, new staff or replacement staff are added
- This is a naturally occurring thing, it's reality
- So, won't this issue continue to present itself each time I add/replace a resource/role to a previously staffed project?