Thank you Michael for your reply.
I have tried this, but every time I open a project from Clarity (Either from the web UI or from the macro buttons inside MS Project) it defaults back to the original settings... even though I had set them for "All New Projects".
Maybe the interface sets them inside the code before every open of a project?
The issue is that tasks created in the web UI, when opened in MS Project, are automatically changed to 0 days duration, like milestones.
What is the best way to debug this interface? Can I set something so logs will be created with readable information?
I thought about opening the MST file and maybe I can save the settings on this file and then it will work, I don't know...
Thanks
Amir