From the Project, open the "Clarity Gantt" (from Open in Scheduler).
Select Create Baseline (from the Camera icon) - You have to have at least one baseline before you can Update a Task baseline.
Once you have your initial baseline, you can then select the tasks you want to re-baseline/update, and just select "Update Task Baseline" from the Camera icon.