So, why have this features at all? It seems to be redundant with Associated Actions, yet it does not have all the functionality of Associated Actions (e.g. an assigned response strategy does not display under My Actions, no notifications, reminders, etc.).
Seems to be a misnomer and redundant. A list of things assigned to resources to complete by a target date is not a strategy - its a 'to-do'/action list.
Why use this feature, at all?
I'm sure someone had a good reason for developing this feature - would like to hear the reason and/or how others are using it before asking to obsolete it. But even if there is a good reason to keep it, customers should have option to not display link if they are not using it. Its about data quality - if you give users the option to use something that the company is not using, users will still find a way to use it, perhaps leaving the areas that they should be using blank.
Dale