We have changed the calculation for the overall status so that schedule weighs 3x more than cost and scope. We've also adjusted the color mappings appropriately. Now the overall status is adjusted and appears correctly on the status reports, but it is incorrect on the portlets (status report indicators and status report listing portlets). More specifically, the value is correct, but the color mapping is incorrect. It appears to be using the original/old color mappings. Any idea how or where we can modify the color mapping for the overall status on the portlets?
Hi,
you need to go to the query behind the portlet (status report indicators) and go into the attributes tab.
Once there, find overall status and click on it.
edit the mappings as needed
Hi Andy,
Yes, that is it. Thank you so much!
Regards,
Lori