Can we make Cost Types WIP Adjustments?

  • 1.  Can we make Cost Types WIP Adjustments?

    Broadcom Employee
    Posted Oct 09, 2014 05:48 PM

    YES !!!

     

    If an actual transaction was posted into WIP with an incorrect Cost Type (Operating or Capital), it can be corrected by using the following steps:

     

    Studio Configuration:

    Configure the 'Cost Type' field on the Task Object for the general properties subpage. 

    This will allow the Project Manager to set a Cost Type value on selected Tasks that is different than the Project-level Cost Type.

    When Transactions are posted or adjusted, if there is a Cost Type value on the task , it will use that value instead of the project-level value.

     

    Changing the Cost Type on the Task:

    1. Login to PPM as a user that has the access rights that allows you to change the Cost Type on a Project Task
    2. Locate the task associated with the actual transaction and change the Cost Type

     

    Making a WIP Adjustment:

    1. Go to 'Create WIP Adjustment' list page ; locating the specific transaction
    2. Open the transaction and click 'Save' button -- NO need to make any changes to the transaction
    3. The transaction will show up on the 'Approve WIP Adjustment' listing
    4. Approve the Adjustment (Now the transaction will have the correct Cost Type associated)
    5. You can see the 'adjusted' Cost Type value on the 'Posted Transaction Review' portlet