  • 1.  Getting Task ID in PX

    Posted Mar 29, 2020 03:01 PM
    Hi,
    I'm trying to get the Task ID in PX but so far I'm unsuccessful..
    I tried a Policy Xpress on an Event level, set on After ModifyUserEvent and also tried on a Task level set on Task Started for a Modify User task, in both cases, I've tried getting the Data Element "Task Number" in "Tasks and Events" --> "Task Information" and each time this element comes empty..

    My version is 14.2.

    Is there some known issue with this or am I doing something wrong?

    Thanks,
    Igor


  • 2.  RE: Getting Task ID in PX
    Best Answer

    Broadcom Employee
    Posted Mar 29, 2020 05:41 PM

    Hi Igor,

    Please check the following Community thread. This is applicable for 14.2

    https://community.broadcom.com/enterprisesoftware/communities/community-home/digestviewer/viewthread?MessageKey=45b0762c-70b9-40d8-bd38-879b13a404d2&CommunityKey=783a8a1e-bb2b-473a-a0c3-7be7b1d92c60&tab=digestviewer#bm45b0762c-70b9-40d8-bd38-879b13a404d2

    Regards,

    Widjaja.




  • 3.  RE: Getting Task ID in PX

    Posted Mar 30, 2020 04:31 AM
    Thank you, this worked just fine!

    Though I still don't understand what is "Task Number" in the PX data is...

    Regards,
    Igor


  • 4.  RE: Getting Task ID in PX

    Broadcom Employee
    Posted Mar 30, 2020 07:38 PM
    Hi Igor,

    Task ID is long and difficult to remember. Task Number is another representation for easy viewing. Please see below documentation for details.

    https://techdocs.broadcom.com/content/broadcom/techdocs/us/en/ca-enterprise-software/layer7-identity-and-access-management/identity-manager/14-3/administrating/system-management/task-status-in-ca-identity-manager/view-submitted-tasks/task-numbers.html

    Regards,
    Widjaja.