How can I modify a report schedule?

Jump to Best Answer
  • 1.  How can I modify a report schedule?

    Posted 12-04-2017 07:32 PM

    Users can send reports by email, either manually or on a schedule.  As an admin can I verify or edit those schedules? Say a user decides weekly is too frequent and wants the report monthly. We are using CA Performance Management 3.0.



  • 2.  Re: How can I modify a report schedule?

    Posted 12-04-2017 08:13 PM

    Ah, I missed that. Thank you for the quick response.



  • 3.  Re: How can I modify a report schedule?
    Best Answer

    Posted 12-04-2017 08:08 PM

    You should be able to modify the schedules from Administration --> Scheduled Emails . Select the schedule you want to modify and Edit