version used: CA workload automation 11.4.3
Can a job statistics report can be automated to be generated and downloaded at a scheduled time everyday ?
I know Workload Automation DE uses BIRT as its reporting tool, and I suspect the same is true for AE. According to this article, I believe you could download the BIRT runtime and create a batch file that triggers the runtime to create the report. Once that is set up you could schedule the execution of the batch job in AE.
Unfortunately autosys doesn't...the user is talking about a specific problem in WCC where reports cannot be scheduled and they don't stick when you logout either...that's just a weird design for something that you would run as often as reports.
Shows you how much I know about AE. "A" for effort I suppose.
Deekshit posted the correct response.
CA support
MarkW