Working with priorities

Jump to Best Answer
  • 1.  Working with priorities

    Posted 24 days ago
    In AWA more or less all objects have the attribute "AE priority". Till now we don't use this attribute or better we use only the default priority 200.
    Has anyone experience with different priorities? Does lead different priorities to worse performance of the AE system because before processing not only FiFo has to be considered?

    Thanks.


    ------------------------------
    Kordula
    ------------------------------


  • 2.  RE: Working with priorities
    Best Answer

    Posted 20 days ago
    Hi Kordula,

    we have the same workflow running for different sized customers (and hence different long runtimes). In the workflow there may be wait situations, for example wait for sync or wait for resource. For individual large customers we increase the priority so that their processing can be completed in the promised time in any case.

    In a processing where wait situations may also occur, we increase the priority of automatic restarts. But I cannot answer at the moment why my colleagues have implemented this in such a way.

    By using different priorities, we have not experienced any difficulties so far.

    Best regards,
    Tim

    ------------------------------
    Automation Evangelist
    Fiducia & GAD IT AG
    ---
    Mitglied des deutschsprachigen Automic-Anwendervereins FOKUS e.V.
    Member of the German speaking Automic user association FOKUS e.V.
    ------------------------------



  • 3.  RE: Working with priorities

    Posted 18 days ago
    Hi Tim,
    sounds good. Thanks for sharing your experience.
    Best regards,
    Kordula

    ------------------------------
    Kordula
    ------------------------------