  • 1.  How to stop showing up the Estimated Run time of jobs

    Posted May 03, 2018 09:25 AM

    Hello Team,

     

    Could you please tell me whether I could stop showing up the Estimated Run time of jobs. Because I don't want to let the user know about the ERT as I feel it is not that accurate to show upon. Instead of making them confused, we have decided not to display that. Is it even possible, if yes, let me know.

     

    Thanks in advance,

    Srujan.



  • 2.  Re: How to stop showing up the Estimated Run time of jobs
    Best Answer

    Posted May 04, 2018 06:15 AM

    No. It's a core feature of Automic and there's no configurable way of hiding it (short of a GreaseMonkey / user.js script to tamper with AWI, client side, which I would personally not do).

     

    Best regards,

    Carsten



  • 3.  Re: How to stop showing up the Estimated Run time of jobs

    Posted May 27, 2018 10:04 AM

    You cannot hide it but you can set it to a non-significant fixed value without calculation at each execution of the object.