How to set up External Dependency - the basics

  • 1.  How to set up External Dependency - the basics

    Posted Jun 14, 2016 10:54 AM
    In this example, the external dependency is set to only run on the 4th of July.

    1. Always set the expected status to ANY_OK in the 'External dependency' tab rather than in the task's dependencies tab.

    Note: ANY_OK covers the following statuses = Ended inactive, Ended skip because of calendar, Ended OK

    dfenfgdu6ybg.jpghttps://us.v-cdn.net/5019921/uploads/editor/tc/dfenfgdu6ybg.jpg" width="872">

    2. This external dependency will only run on the 4th of July.  Any other day, it will be skipped:

    fafbunzd6grw.jpghttps://us.v-cdn.net/5019921/uploads/editor/a7/fafbunzd6grw.jpg" width="566">

    3. Leave the status blank in the task's 'Dependencies' tab.

    yhi2g79a26sw.jpghttps://us.v-cdn.net/5019921/uploads/editor/9j/yhi2g79a26sw.jpg" width="775">