    We are using Application Manager v9.2

    I have an AppWorx Chain with 3 jobs in it. I have declared a prompt value: ItemFile_{#timestampYYYYMMDDHHMMSS}.txt (this is for the chain)

    First job takes this prompt and executes a program to generate a file. It is creating ItemFile_20190913110935.txt
    Second job takes the same prompt and executes another program. It is failing because, the same prompt now is evaluated to ItemFile_20190913111022.txt

    If you see the file name, the timestamp is different. hence the second job is failing.

    Is there any way I can instruct application manager to evaluate this prompt only once at the beginning of the process and not for each job.
    ------------------------------
    Thanks,
    Ug.
    ------------------------------


  • 2.  RE: Evaluate Prompt only once

    Posted 6 days ago
    Can some one please let me know if there is any option for this?


  • 3.  RE: Evaluate Prompt only once

    Posted 6 days ago

    Yes, create a prompt at the chain level and pass it to the 3 jobs using the prompt number, ex: #1, in the value column on the job.

     

     

    Angela Hoffman

    Computer System Analyst/Programmer II

    UIT Enterprise Services Group

    920 Technology Blvd (Nopper Building)

    406-994-7399