 Tasks Greyed out in Timesheet with New UX

Chris Flynn's profile image
Chris Flynn posted Jan 13, 2021 07:30 AM
Hi Folks,

I am using Clarity PPM 15.7 and I have some PM's trying to add tasks to there timesheets but they are greyed out. The User, Project and Tasks are open for time entry. Not sure what else could be causing this. Any ideas would be greatly appreciated.

Thanks.
Jose Ignacio Mugica's profile image
Broadcom Employee Jose Ignacio Mugica
Hi Chris,
Can you check if they do have a parent task which OTE flag is off?
Ensure the track mode of the project is PPM as well 
Thanks
Joxi