Products
Applications
Support
Company
How To Buy
Skip to main content (Press Enter).
Sign in
Skip auxiliary navigation (Press Enter).
Register
Skip main navigation (Press Enter).
Toggle navigation
Search Options
Home
Communities
All Communities
Enterprise Software
Mainframe Software
Symantec Enterprise
Blogs
All Blogs
Enterprise Software
Mainframe Software
Symantec Enterprise
Events
All Events
Enterprise Software
Mainframe Software
Symantec Enterprise
VMware
Water Cooler
Groups
Enterprise Software
Mainframe Software
Symantec Enterprise
Members
Clarity
Private Community
View Only
Community Home
Threads
89.1K
Library
3.5K
Events
4
Members
1.6K
Back to {0}
Tasks Greyed out in Timesheet with New UX
Thread closed by the administrator, not accepting new replies.
Add a tag
x
User Tags may not contain the following characters: @ # $ & :
Chris Flynn
posted Jan 13, 2021 07:30 AM
Hi Folks,
I am using Clarity PPM 15.7 and I have some PM's trying to add tasks to there timesheets but they are greyed out. The User, Project and Tasks are open for time entry. Not sure what else could be causing this. Any ideas would be greatly appreciated.
Thanks.
Broadcom Employee
Jose Ignacio Mugica
posted Jan 13, 2021 08:34 AM
Hi Chris,
Can you check if they do have a parent task which OTE flag is off?
Ensure the track mode of the project is PPM as well
Thanks
Joxi