  • 1.  Clarity - Timesheets Changing Status

    Posted Feb 21, 2012 02:48 PM
    I have a manager that is approving her submitted timesheets one at a time after reviewing them, only to find them back in submitted status a few hours later. She stated she is doing everything correctly. This has happened to another manager in the last year, but these are the only two instances I've heard of.

    We are on 12.0.5.5350 FP00.27 001.

    Anyone have any thoughts?

    Is there an 'activity' log that I can review and find where she actually did approve all her timesheets on Monday?

    Thank you!


  • 2.  RE: Clarity - Timesheets Changing Status
    Best Answer

    Posted Feb 21, 2012 11:06 PM
    PRTIMESHEET table : check for following fields

    PRAPPROVEDBY
    PRMODBY
    PRMODTIME
    PRSUBMITTEDBY

    Regards
    NJ


  • 3.  RE: Clarity - Timesheets Changing Status

     
    Posted Feb 27, 2012 04:32 PM
    Hi Julie,

    Did NJ's response help you resolve? If so pelase mark the post as Accepted Solution.

    Thanks!
    Chris


  • 4.  RE: [CA Clarity General Discussion] RE: Clarity - Timesheets Changing Statu

    Posted Feb 28, 2012 07:30 AM
    Yes, the response helped us get the data we needed to make our point.

    How do I mark the post as “accepted solution”? I’m afraid I’m not seeing it.

    Thank you!

    From: CA Clarity Global User Community [mailto:CommunityAdmin@communities-mail.ca.com]
    Sent: Monday, February 27, 2012 3:32 PM
    To: mb.2277340.97594939@myca-email.ca.com
    Subject: [CA Clarity General Discussion] RE: Clarity - Timesheets Changing Status

    Hi Julie,

    Did NJ's response help you resolve? If so pelase mark the post as Accepted Solution.

    Thanks!
    Chris