Hi Everyone,
% Complete in one of the sub tasks is not getting rolled up to the % complete in "Parent Task". Is there a job runs against or it is an issue ?
The % Complete method can be set to manual, effort or duration.
Here some information on the 3 methods:
CA PPM Tuesday Tip: How do the three % Complete Calculation Methods Work