CA PPM: % Complete in "Sub Task" is not rolled up to the % Complete in Parent Task

  • 1.  CA PPM: % Complete in "Sub Task" is not rolled up to the % Complete in Parent Task

    Posted Jan 16, 2019 10:02 AM

    Hi Everyone, 

     

    % Complete in one of the sub tasks is not getting rolled up to the % complete in "Parent Task". Is there a job runs against or it is an issue ? 



  • 2.  Re: CA PPM: % Complete in "Sub Task" is not rolled up to the % Complete in Parent Task

    Broadcom Employee
    Posted Jan 16, 2019 10:08 AM

    The % Complete method can be set to manual, effort or duration.

    Here some information on the 3 methods:

    CA PPM Tuesday Tip: How do the three % Complete Calculation Methods Work