Referring to
Reporting on Actuals/ETC's and cost/bill rates
49625187
just wondering again....
v12.0 SP 6 admin guide
Rate Matrix Extraction Job
This job extracts rate matrix information and populates the rate matrix
extraction tables. Run this job each time the rate matrix has changed, when the
financial properties of a project have changed, or when resources have been
added to an investment.
v12.1 SP1 admin guide
Rate Matrix Extraction Job
This job extracts rate matrix information and populates the rate matrix extraction
tables. Run this job each time the rate matrix has changed, when the financial
properties of a project have changed. There is no need to run the job when a resource is
added to an investment.
how will the rates for the resource added recently to a invest team get updated to the NBI_PROJ_RES_RATES_AND_COSTS TABLE if the job is not run?
Say you have created a project and financially enabled it and run the job. Then you add resource to the team.
Martti K.