DX Application Performance Management

  • 1.  Heuristics metrics and variance metrics

    Posted Nov 01, 2018 06:26 PM

    Hi!

     

    I'm migrating APM from 9.7 to 10.7 and a I have a doubt. There are a lot of Heuristic's metrics and in current version they are not exist. My question is: Are there any way to the Variance metrics using olds metrics as historic?.

     

    Thanks in advance!

     

    Best regards.-



  • 2.  Re: Heuristics metrics and variance metrics

    Broadcom Employee
    Posted Nov 04, 2018 09:28 AM

    Dear Oscaldo:

      What are some of the metrics that are missing?

     

    Thanks

    Hal German



  • 3.  Re: Heuristics metrics and variance metrics
    Best Answer

    Broadcom Employee
    Posted Nov 04, 2018 07:05 PM

    Hi Osvaldo Gomez,

    In APM 10.x Differential Analysis/Variance replaces the previous heuristics/baseline metrics functionality, to give an improved method of monitoring application stability through historical data analysis. This KB has some details: Heuristics is disabled or not available in APM 10. - CA Knowledge 

    I am not not sure if it is possible to map new Differential Analysis/Variance metrics to old heuristics/baseline metrics. Guenter Guenter_Grossberger might know more on that.  

    Hope that helps

    Regards,

    Lynn



  • 4.  Re: Heuristics metrics and variance metrics

    Posted Nov 06, 2018 08:27 AM

    Hi, 

    Thanks very much for you're replies. I assumed it was not possible to map both kinds of metrics but I must to explain it to our customer.

     

    Best Regards.