  • 1.  Planning and historical feedback in Rally

    Posted Jun 13, 2018 09:44 AM

    We are using Rally for our DevOps implementation tracking and progress of SCRUM team development

    1. Is there a way to get recommendations for SCRUM teams during iteration planning for pulling user stories based on past performance of the SCRUM team on previous iterations. Example: Recommend to have the planned velocity at a certain percentage as historically the SCRUM team is able to deliver up to this planned velocity.

     

    2. At the end of an iteration based on the accepted US for the iteration, the burndown chart analysis etc. providing retrospective items to the SCRUM team to take care of in next iterations.



  • 2.  Re: Planning and historical feedback in Rally
    Best Answer

    Broadcom Employee
    Posted Jun 14, 2018 03:59 AM

    Hi,

     

    I think you might want to take a look at the Velocity Chart. It displays the work completed in past iterations to make it easier to anticipate how much work can be completed in future iterations. You can find more information about it here Velocity Chart | CA Agile Central Help 

     

     

    This article provides some very broad outlines that might be of interest, but you may already have your own practices Retrospect Your Iterations | CA Agile Central Help 



  • 3.  Re: Planning and historical feedback in Rally

    Broadcom Employee
    Posted Jun 14, 2018 11:26 AM

    Hi Kumar,

    To add to West's recommendations, you may want to check out this post as well:

     

    Planned Velocity 

     

    Thanks,

    Sagi