Clarity

  • 1.  15.3 New UX Resource management booking message

    Posted Sep 12, 2017 10:10 AM

    Hi,

     

    I just upgraded to 15.3 and in new UX resource management we are getting below message. But we only use soft booking in our application. What will be the results of running the job that is mentioned in the message?

     

     

     

    Thanks,

    Shiva



  • 2.  Re: 15.3 New UX Resource management booking message
    Best Answer

    Broadcom Employee
    Posted Sep 12, 2017 10:41 AM

    Hi Shiva,

     

    See the documentation https://docops.ca.com/ca-ppm/15-3/en/using/getting-started-with-the-ca-ppm-new-user-experience/new-user-experience-reque… 

     

    You cannot use mixed bookings in new UX

     

    Regards

    Suman Pramanik 



  • 3.  Re: 15.3 New UX Resource management booking message

    Posted Sep 12, 2017 11:26 AM

    Thanks Suman, The job mentioned will convert the mix bookings into which ever booking type we used. Let me run the job.