Report Prerequisites
Verify that you have completed the following prerequisites before you run this report:
- The Load Data Warehouse and Load Data Warehouse Access Rights jobs must be run before you run this report. If the Data Warehouse is not populated, the report displays a message that there are no matching records. Also, most of the report parameters do not display options.
- The report displays resources that are set up to enter time in CA PPM. If the resource does not have a timesheet in CA PPM for the time period and the timesheet status was selected when running the report, then the resource displays in the report with a timesheet status of Open with zero hours. It is not necessary to have at least one timesheet for the resource to display in the report.
- The resource is considered set up for time entry if the following conditions are met on the resource: the Open for Time Entry field is checked; the track mode set to Clarity or Other; the date of hire is blank, prior to the time period, or within the time period; and the date of termination is blank, after the time period, or within the time period.
- The investment must have the Open for Time Entry field checked and the track mode set to Clarity in order to enter time against the investment. If the investment is a project, then the Open for Time Entry field on the task must also be checked in order to enter time against the task.
- The investment must have at least one resource assigned to a task in order for the resource to enter time against the investment and for it to display in the report. For projects, the resource must be assigned to a task in the Gantt, unless the project has an effort task with resources automatically assigned. For investments other than the project, resources added to the team are automatically assigned to an effort task for the investment.
Note: Effort task is a task with the Task ID of "~rmw".
In a timesheet, resources may also assign themselves to tasks if they are team members on the project and the Prevent Unassigned Timesheet Tasks field is unchecked on the project. This field is in the time and staff section of the settings properties on the project. They can also create unplanned tasks in a timesheet if they are a team member on the project and have the appropriate permissions (Project – Edit Project Plan).
- The timesheet hour amounts are calculated based on the time slice with the name DAILYRESOURCETIMECURVE (Administration/Data Administration-Time Slices).
Are the TIMESLICES upto date?
NJ