Rally Software

Expand all | Collapse all

How to alter the actual start date and actual end date at feature level!

  • 1.  How to alter the actual start date and actual end date at feature level!

    Posted Oct 03, 2016 03:05 AM
    How can i alter the actual start date and actual end date! We need so that we can enter the features that we delivered before we started using Rally! We have created one dummy user story for each feature. But as soon as we put user story in Accepted state, the actual start date and end date assume todays date!  

    We need to sync the actual start date and actual end date  in Rally with the dates when the feature got delivered before we used Rally! 

    Please help


  • 2.  Re: How to alter the actual start date and actual end date at feature level!

    Posted Oct 03, 2016 02:39 PM
    That is set as a read-only date and AFAIK only planned can be changed, not actual.