What's the best way to send out one single project level action item for task(s) creation all across the system

Jump to Best Answer
  • 1.  What's the best way to send out one single project level action item for task(s) creation all across the system

    Posted 10-14-2015 09:49 AM

    Hi all,

     

    any suggestion on sending out one action item per project when tasks are created against it?

    Gel script to get all tasks for a given project then parse it out?

     

    Thanks,

     

    Tai



  • 2.  Re: What's the best way to send out one single project level action item for task(s) creation all across the system
    Best Answer

    Posted 11-02-2015 02:38 AM

    Hi Tain,

     

    There are no out of box task based notification so you have to send email using gel script only.

     

    Regards

    Suman Pramanik



  • 3.  Re: What's the best way to send out one single project level action item for task(s) creation all across the system

    Posted 11-02-2015 08:59 AM

    Thanks Suman.