When I auto scheduled my project this one task's end date was moved out past today even though the task was showing 100% Complete, a status of Completed, and an ETC of 0.00.
When I clicked on the ETC for the task I saw that it was 0.000016. When I typed over the ETC and changed it to “0” and auto scheduled it worked right.
Is there a way to get Clarity to round the ETC down to 0 when it's so close to 0?
Thanks.